Third Party Green & Energy Code Reviews

University Park Energy Conservation Code

Highland Park Energy Conservation Code

Plan Review

Email a full set of plans & relevant cut sheets to mark@dfwgreencode.com.

The plans should indicate:

  • R-value & location of insulation
  • U-factor & SHGC of the windows
  • HVAC sizing & SEER rating

After my review I will provide you with an IC3 report and a letter to give to the Building Official.

Inspection

An inspection must be done at insulation rough-in before sheetrock is installed on the walls.  A duct tightness test must be performed on new HVAC systems unless the system is fully within conditioned space.  A blower door test is required for all new construction.  I do not perform these tests.  Go to the testing tab for for a list of certified Raters that I have worked with in the past.  A final inspection is also required.

After my inspection I will provide you with a letter you give to the building inspector.

Plan Review

Email a full set of plans & relevant cut sheets to mark@dfwgreencode.com.

The plans should indicate:

  • R-value & location of insulation
  • U-factor & SHGC of the windows
  • HVAC sizing & SEER rating

After my review I will provide you with an ResCheck report to give to the Building Official.

Inspection

An inspection must be done at insulation rough-in before sheetrock is installed on the walls.  A duct tightness test must be performed on new HVAC systems unless the system is fully within conditioned space.  A blower door test is required for all new construction.  I do not perform these tests.  Go to the testing tab for for a list of certified Raters that I have worked with in the past.  A final inspection is also required.

After my inspection I will provide you with a letter you give to the building inspector.