Window poly-seal
Required for:
New construction
Additions
Remodels that include any of the following:
Eave baffles
Top plate poly-seal
NFRC window sticker
Bottom plate poly-seal
Insulation dam
Insulation netting at attic wall
Plan Review
Email a full set of plansand any relevant cut sheets to mark@dfwgreencode.com
The plans must include:
These are not required but helpful
2021 IECC Highlights - climate zone 2A (Dallas, Tarrant, Ellis & Johnson Counties)
2021 IECC Highlights - climate zone 3A (all other North Texas Counties)
2018 IECC Highlights - climate zone 3A (all of North Texas)
2015 IECC Highlights - climate zone 3A (all of North Texas)
After my review I will provide you with an IC3 report for new construction or a REScheck report for additions and remodels. You will also receive an energy compliance path form if required by your city to turn in with your permit application.
Inspections
Energy code inspections are required throughout various phases of construction. The first is at rough insulation prior to drywall. Please note that some cities require an additional inspection of the poly-seal prior to the insulation being installed. I will then need to do a energy final inspection after the following are complete:
Below is an overview of best practices and some of the items I will be looking at during my inspections.
Insulation and Sealing
Houses are built with various barriers to limit the movement of air, heat and moisture between conditioned and unconditioned space.
The moisture barrier consists of the roofing, the exterior sheathing and vapor barrier under the foundation. The sheathing will either be wrapped with a water resistant fabric such as Tyvek or have an integral moisture barrier such as ZIP board. A vapor barrier should be installed under the slab or on the soil in a pier and beam foundation. If not controlled, excess moisture and humidity can lead to inefficient HVAC performance and eventually mold growth.
The air barrier is generally the finished gypsum board walls and ceilings, and sub-floor in pier and beam foundations. Since there are many penetrations in the gypsum board such as outlets, light fixtures, registers, etc., it is essential that the framing behind the drywall be properly sealed. Poly-seal is needed at the bottom plates at the slab or sub-floor, and at the top plates where the gypsum board will be placed. Any gaps in the studs or exterior sheathing should be sealed as well. All windows and exterior doors should be poly-sealed around the shim space at the edges. All penetration in the top and bottom plates along with any thru-stud penetrations should be sealed. Please note that any penetrations in framing cavities should be sealed with fire retardant poly-seal. This will keep any potential fires from spreading into adjacent framing cavities or the attic. Low-expansive poly-seal should be used on the windows and plates.
The thermal barrier, also known as the thermal envelope is where the insulation is placed.
Wall insulation must completely fill the stud cavity. It should be the corresponding size for the stud center width and be the proper depth. If the walls are framed with 2x4, then R13 or R15 is appropriate. If 2x6s are used, the insulation will need to be R19 or R21 to be in contact with both the sheathing and gypsum board. Fiberglass batt, mineral wool, blown-in-blanket fiberglass or cellulose and open-cell spray-foam are all commonly used insulating materials.
The attic insulation is probably the most critical due to the constant exposure of the roof to the sun. There are several ways to insulate the attic. Attics are either ventilated, while being outside of the conditioned envelope, or non-vented or encapsulated within the conditioned envelope.